Change Order #1 to Scull Construction Services Inc. for Rapid City Landfill Citizen Campus Construction, Project No. SW01-2012, for an increase of $178,231.72.

Summary:

Increase to contract based on actual quantities installed. 

Funding Source & Fiscal Impact (if applicable):

7102 Solid Waste Disposal; 7103 Solid Waste MRF/Compost